FLEX-GOB LED Module Gaps: Root Causes, Proven Fixes and a Complete Installation Guide

FLEX-GOB LED modules combine the flexibility of soft modules with the protection of glue-on-board encapsulation, which makes them a popular choice for fine-pitch indoor displays, creative shapes and irregular walls. Yet even well-made modules can show visible gaps once they are on site. The good news is that most gaps are not a product defect. They are installation and surface-condition problems, and nearly all of them can be corrected with simple, low-cost measures.

This article breaks down why gaps appear, ranks the four most effective remedies used in the field, and closes with a practical installation workflow that keeps module surfaces level and seams tight from the first cabinet to final commissioning.

Why Gaps Appear in FLEX-GOB Installations

Gaps rarely come from a single cause. In most projects they are the result of several overlapping factors.

  • Uneven substrate.Walls, floors, columns and custom frames are seldom perfectly flat. A surface that varies by even a few millimetres will push some modules forward and let others sit back, creating a visible step at the seam.
  • Protruding magnets.Magnetic modules rely on rare-earth magnets for front and rear service. If a magnet protrudes beyond the module face, the module can no longer sit flat against its neighbour, and the gap opens at exactly that point.
  • Recessed areas inside a module.Where a module carries several protruding magnets, the zones between them effectively become recessed. The module surface is physically flat, but the magnet pattern lifts part of it and leaves the rest low.
  • Installer technique and experience.When the gap between an upper module and a lower module is large, the most likely explanation is that the module was not properly installed. Fit, seating order, magnet alignment and tightening sequence all depend on the skill of the crew, and this is usually a technique issue rather than a material issue.

Once you know which of these factors is at work, the fix becomes obvious. The four methods below cover the full range of cases we see in the field.

Method 1: Tape Shimming to Level Uneven Surfaces

For uneven areas, or for areas where magnets protrude, tape can be used to raise the recessed areas and level the module surface. This is the fastest and least invasive correction available, and it requires no modification to the module itself.

The technique is straightforward. Identify the low points on the mounting surface or between the protruding magnets, then build up those low points with tape until the module face sits level with its neighbours. A practical example makes the logic clear: if a module has multiple protruding magnets, tape can be used to raise the area between two protruding magnets. That lifts the recessed zone, levels the module surface and improves the situation immediately, without touching the magnet or the encapsulation.

Two rules matter here. First, use a tape with consistent thickness and good compression resistance, so the shim does not creep or collapse after weeks of thermal cycling. Second, keep the build-up symmetrical. A single thick patch at one corner will tilt the module and simply move the gap to the opposite edge.

Tape shimming is ideal for retrofits and for sites where the wall cannot be re-plastered. It is also the correct first response before any more invasive measure is considered.

Method 2: Correcting Large Gaps Between Upper and Lower Modules

When the gap between two up and down modules is large, the cause is almost always installation. In most cases the module was not properly installed, and the problem traces back to the installer’s technique and experience rather than to the module or the magnet.

The fix is procedural, not mechanical.

  • Re-check seating.Confirm that the upper module is fully engaged with its mounting surface or frame, and that no magnet is riding on a high point.
  • Verify the tightening sequence.Seat modules from a reference edge or from the centre outward, so slack is pushed to the perimeter instead of accumulating at a seam.
  • Inspect the frame.A frame that is out of tolerance will open a gap no matter how carefully the module is fitted.
  • Assign an experienced installer to critical seams.Large-format walls and creative shapes should not be entrusted to a crew still learning the product.

A short pre-installation briefing, a reference module for each wall, and a first-row sign-off before the crew continues upward will eliminate most of these gaps before they ever appear.

Method 3: Secondary Magnet Reinforcement

Where the gap is caused by insufficient holding force rather than by surface condition, secondary magnet reinforcement is the answer. Magnets are added to the modules in the module production workshop, and the magnets are tightened again after GOB processing, so the added attraction is secured against the encapsulation rather than sitting loose behind it.

This method does two things at once. It increases pull force at the points where the module tends to lift, and it reduces the chance that heat cycles or vibration will gradually open a seam. Because the reinforcement happens in the workshop and is re-tightened after glue-on-board processing, the result is repeatable and inspectable rather than improvised on site.

Use this option when the gap returns after tape shimming, when modules sit on a surface with a slight convexity, or when the display is mounted where air movement and temperature swings are significant.

Method 4: Loosening the Magnets Above the Silicone Kit

Sometimes the magnet is simply too buried. In that case, loosening the magnets so that they protrude above the silicone kit restores the contact the module needs. A magnet that sits flush with or below the encapsulation cannot pull the module firmly against the frame, so the face floats and the seam opens.

The adjustment is small, but the effect is immediate. The magnet must still be held securely; it should protrude enough to make contact, not so far that it becomes the highest point on the module and creates a new gap of its own. After adjustment, re-check the module against a straight edge before it goes back on the wall.

Why-Gaps-Appear-in-FLEX-GOB-Installations

Step-by-Step Installation Workflow

A disciplined sequence prevents most gap problems before they start.

  1. Survey the substrate. Map high and low points with a straight edge and record where shimming will be needed.
  2. Establish a reference row. Install the first row to a laser line, and do not proceed until it is level and sign-off is complete.
  3. Check every module before mounting. Confirm magnet height, encapsulation integrity and face flatness.
  4. Shim low points with tape. Build up recessed areas evenly, especially between protruding magnets.
  5. Seat modules from the reference edge outward. Push slack to the perimeter, never into a seam.
  6. Reinforce where holding force is short. Apply secondary magnets in the workshop and re-tighten after GOB processing.
  7. Adjust buried magnets. Let them protrude above the silicone kit where contact is weak.
  8. Inspect seams under angled light. A raking light reveals steps that a front view hides.
  9. Log every correction. A record of which modules were shimmed or reinforced speeds up service and warranty work.

 

Quality Verification Checklist

Before commissioning, walk the wall and confirm the following.

  • No visible step at any horizontal or vertical seam under angled light.
  • Magnet contact is firm at every module, with no floating corners.
  • Tape shims are symmetrical, compressed and stable.
  • Modules reinforced after GOB processing show no loose magnet.
  • The surface reads as one continuous plane from normal viewing distance.

Frequently Asked Questions

Are gaps in FLEX-GOB modules a quality defect?

Usually not. Uneven surfaces, protruding magnets, recessed areas and installation technique account for the large majority of cases.

Can tape really fix a gap?

Yes, for surface-level unevenness and for recessed zones between protruding magnets. Tape raises the low area and levels the module surface without modifying the product.

What if the gap is between an upper and a lower module?

Treat it as an installation issue first. Re-check seating, tightening sequence and frame tolerance, and put an experienced installer on the seam.

When should magnets be reinforced?

When holding force is the limiting factor, or when a gap reappears after shimming. Reinforcement is done in the workshop and re-tightened after GOB processing.

Conclusion

Gaps in FLEX-GOB installations are predictable, and therefore preventable. Level the surface with tape, seat modules properly, reinforce the magnets where holding force falls short, and let buried magnets protrude above the silicone kit. Combine those four measures with a disciplined installation sequence, and the result is a seamless, flat and serviceable LED wall that performs as designed for the life of the project.

Facebook
Pinterest
Twitter
LinkedIn

Leave a Reply